News (before 28 January 2010)


Architectural Plan

Click on image to enlarge.
21 January 2010 - Everyone has been pitching in here for the final stretch...

Lynne has been especially busy this week, and with Anne's help they finished painting the trim that sits on top of the wall which divides the production area from the retail space. They also painted the legs of and washed the exteriors of all five brite tanks, which allowed us to move them into place inside of the cellar this evening.

I ran power to the grain mill and hose from the bulk C02 tank to the secondary regulators inside of the cellar. I also began work on the grain hydrator.

Shaun has been working on welding up the work platform which will sit between the brew kettle and the mash tun,

My dad turned a coulpe of teflon valve seats on his lathe and is constructing the table which will be mounted in the retail space inside of the front window.

Time to order some ingredients for the first few batches of beer!



16 January 2010 - The state excise officer inspected F8 on Friday and we were told to expect our state license paperwork in the next week or so. Now, with the exception of a couple of local inspections, we have the green light and the only things stopping us from opening our doors is me finishing the work necessary to brew beer. This means that barring any disasters, we should be opening our doors in February - WOOT!

Of course this means we are in crunch mode to finish up! Now that the production floor is finished, Lynne, Annabelle, and I moved everything out of the cellar, putting those pieces which could be located in their final locations in place and finding temporary places for everything else. Lynne continued painting the trim that covers the tops of the walls. I acid etched the floor in the cellar so that it can be sealed with epoxy paint. I also worked on hooking up equipment, including the glycol and temperature controls for the two open top fermentors.

The list is growing shorter, but there is still a fair amount of work to be done...



10 January 2010 - Sorry for the lack of pictures in this entry, hopefully the news will be enough. Last friday marked the end of the concrete floor's curing period and so this weekend I etched the floor in preparation for applying the epoxy coating. After a few days of cure time, the equipment will all be moved back into place and be hooked up for cleaning and our first test brew. You cannot believe how excited I am about this goal!

I finished attaching the stainless steel skins to the outside of the mash tun and only need to complete the construction of the cover to call it done. Shaun has begun work on welding the steel for a platform that will sit between the brew kettle and the mash tun, so that should be completed at about the same time that the equipment is being put back into place.

Lastly, we've now had over 2000 hits to our web site - interest continues to brew :-)

4 January 2010 - The new year is here and this is destined to be the year of Figure Eight Brewing!

On the 30th, the Post-Tribue had a nice full page article about the locally crafted beers in our region of NW Indiana. Figure Eight was mentioned a couple of times along with the other micro breweries and brew pubs in this area.

Mixed with the new year celebrations, festivities, and visits by friends and family, I finished drilling the endless holes in the sparge head and tested it by running water through it (as seen in the picture) and I am very happy with the spray pattern and coverage.

27 December 2009 - This has been a wonderful holiday so far. Our family and friends have been joining us for food and festivities nearly continually and it has been very fun...

Even with all of these activities, I've managed to make some progress at F8, primarily on the mash tun. As shown in the first image, the sparge head is assembled, but not yet drilled. The mash tun frame is insulated and mostly skinned with stainless steel sheeting (one side remaining). The sparge head is also shown fitted into the top of the mash tun. The covers (two halves) for the mash tun are partially completed, but not shown.

We had a number of black t-shirts silk screened a while back and have a few left, but have made a second run with some additional colors and they are due to be completed soon. So, even before we will be allowed to sell our fine hand crafted brews, we will have our F8 pint glasses and t-shirts available to those who will want to avoid the lines at our grand opening (to be announced in the not too distant future). Look for these items on our web site soon :-)


20 December 2009 - I'm done with the production floor, now waiting for the concrete to cure before applying the epoxy sealer. I've also decided not to slope the cellar floor as it is not as bad as the production area and will not see as much water. I'm moving on to getting the remaining projects done during the curing phase in order to start making beer as soon as possible. This included an initial first pass of cleaning up the huge amounts of dust which were made during the concrete work.

I am now working on installing the glycol protective railing (seen hanging in the floor picture) which Shaun was kind enough to weld up for me. The first step was to prep it for painting with POR-15. This railing will be located just inside of the door between the production area and the retail space, protecting and supporting the glycol plumbing from being bumped into by people who walk through this "hallway".

Our F8 pint glasses arrived last week and I think that they turned out perfectly. We will have these available for sale, along with our F8 growlers and t-shirts. This reminds me that I need to start setting up the online sales web page...

This weekend was busy with preparations for having of a number of our closest friends over for an evening and morning of food, drink, fun, and festivities. The event went very smoothly, complete with climbing videos, bouldering in our basement cave, playing of Beatles Rock Band II, eating, etc. It was a wonderful time!


14 December 2009 - The new floor doesn't drain as well as it should as there are some high spots which cause the water to pool. The installers setup to come in on Monday to grind the high spots in order to correct the problem. In an attempt to contain the dust, our friend Cameron (who was over for Joel's 13th birthday party and to help us with our annual stuffing of Swedish sausage) helped me errect an enclosure of 2x4s and plastic on Sunday.

It quickly became apparent that grinding with a small 10 inch diamond wheel grinder was not going to solve the problem, but it did create a beautiful finish of exposed aggregate, which I'm thinking would be nice to seal with a clear coat rather than tan. I'm holding off on that decision until the floor drains properly as I'll have plenty of time to decide later as the concrete still has to cure for another 20+ days before sealing. In order to solve the drainage problem, I have Northwest Indiana Concrete Cutting coming Tuesday to grind the floor with a large machine that will hopefully take care of the problem once and for all.

This whole new floor thing has kept me at a pretty high stress level over the past few days as the time and expenses rack up without the floor problem actually being solved. Hopefully everything will be good in the end and it won't take too long to happen.



11 December 2009 - So my efforts to do the sloping of the floor without professional help failed and with many regrets I called the pros from dover in to do it right. It was a bit cathartic to tear out what we had spent so much time, effort, and money to install only a few days earlier, but in the long run it will be worth it.

Other projects which I've been working on this week have been to finish wiring the controllers for the glycol solenoid valves (seen in the first pic of this installment) and to hang the neon F8 sign which I had made by a local artisan. The iPhone does not do the colors of the sign justice, the F is red and the rope is yellow, but you get the idea.

On the planning front, this new floor has just become the long stick in the timing of our opening. While I had been planning on opening in January, we now have to wait 28 days for the floors to finish curing before we can put the epoxy seal coat down. Sigh... At least I will have plenty of time to finish all of the other small projects before we open.




6 December 2009 - This past week and this weekend were spent working on the mezzanine and staircase railings and the half wall trim cap. With Joel's help on Saturday morning, I finished the railing and included a gate above the cellar door in order to allow materials to be forklifted to the upper level. The railings turned out great and I'm glad to have them done.

Lynne worked on painting trim and now has a bunch more to do as I completed most of the half wall trim cap, with only the section above the cellar door left to complete, the tanks being in the way of working in this area.

The floor epoxy which I had hoped to have for this weekend did not arrive as the company I ordered it from mistyped our zipcode and the paint made a detour to Ohio. Hopefully it will arrive this week. The next couple of major things left to do before brewng beer are to epoxy the production floor, insulate / cover the mash tun, and slope / epoxy the cellar floor. There are of course a number of small jobs which also need doing, but they are all sub-day efforts.


2 December 2009 - A quick mid-week update now that December is off to a rolling start. As mentioned, I've been working on putting up the protective railing around the mezzanine level and if I do say so, I think it looks pretty nice. In building it, I've also come up with a scheme for trimming the top of the walls, which Lynne has been asking about as she wants to paint it. When I asked if she wanted to paint the railing, she said "no". I don't blame her, besides, the natural wood looks nice.
30 November 2009 - I love long holiday weekends! We took Saturday off and went climbing at ClimbOn in Homewood, where our climbing friend Bob joined us, followed by dinner at the neighboring Flossmoor Station Brewery. We had not been to ClimbOn since last spring as it is our winter weekend climbing destination, when outdoor soccer no longer occupies my Sunday afternoons. They have an excelent facility and the owners and people there are great. The brewery in the neighboring city of Flossmoor has good food and brews some outstanding beer! My favorite for the evening was their Black Magic IPA.

On Sunday, I got going early on finishing the work of sloping the main production floor and after a quick five hours I was ready to come home and relax...

Unfortunately, with all of the equipment moved off of the floor and blocking access to the cellar, work on sloping that floor will have to wait until the main floor cures, is epoxied, and the equipment returned. This leaves work on the mezzanine and staircase rails until that time.

27 November 2009 - Thursday was Thanksgiving which means two things, dinner with family and friends with lots of pies, and that December is near. Turkey dinner at my parents was fabulous as usual and included four pies. This meant that with my folks, my brother and his wife, our friend Cameron, and the three of us, there was a 1:2 pie to person ratio which is pretty good:-)

Backing up to the day before Thanksgiving, Lynne and Annabelle had apparently been planning a surprise for me for some time, and Wednesday Lynne and Joel told me that we had to go to Anne's place as she had a surprise for me. I had no clue what to think about this and so was a bit skeptical, but was pleasantly surprised to find that they had ordered me a set of pilsner glasses with the F8 logo engraved on the sides along with a pair of pitchers similarly dressed. As if this was not enough, they proceeded to bring out 14 different beers and a plate of cheeses, etc. in order to have a beer tasting. The purpose of the beer tasting was to help bring Anne up to speed on the various varieties of beer out there. We had the gamut from Killian's Red to Stone Imperial Russian Stout, to some tasty Belgiums - YUM!. Great fun, a wonderful surprise and a great evening. Thanks go to both Anne and my wonderful wife Lynne!

Over the past few days, I've been preparing to slope the floors towards the trench drains so that I don't end up with pools of water or beer in the corners. This of course means that I had to move all of the equipment out of the production area, get a mortar mixer, cement, and sand. Joel helped me do some of this and today, he was a tremendous help mixing the mortar while I spread it on the floor. Working from about 10a 'till 6p, we managed to do a bit more than half the floor. I hope to finish the rest before the end of this weekend.




23 November 2009 - The health department requires us to have a hand wash (only) sink in addition to our large three tub sink. I had purchased a stainless hand sink near the beginning of this effort before I knew that the bathroom would be furnished by the building owner. This small sink turned out to be perfect and it fit in just right, next to the other plumbing.

Last week, when the weather was being typical for the midwest (cold, overcast, damp, and generally miserable), Lynne began work on filling nail holes and painting the door trim. So when the weather this weekend was beautiful and sunny, staying inside painting was not an option.

Over the weekend, I installed the freon lineset for the walkin cellar and began evacuating them to both ensure that the many welds of the 1-1/8 inch copper tubing were good, and to remove any moisture and air in preparation for filling them with R22 refrigerant. In the bottom picture, the two linesets can be seen running from the rear wall of the building (right) across the wall above the staircase, the cellar lineset continuing to the front of the building, and the glygol chiller lineset turning down to run to the chiller under the stairs.

Last night, after determining that the lineset was sealed and ready, I charged the system with freon, making many trips between the increasingly cold cellar, the circuit breaker panel, and the condensing unit outside the building in the chilly night air, made chillier by the blowing of the condenser's fan.

Having the two refrigeration systems now working makes for a couple of big check marks on my list of major things to do before we can begin brewing and eventually open our doors. The major items left on the list are:

  • level the floors toward the floor drains
  • seal the floors
  • construct the stair and mezzanine level railings
  • insulate and shroud the mash tun
  • position all of the tanks and hook those which are cooled to the glycol
  • BREW SOME TASTY BEER :-)

  • 19 November 2009 - What with a long weekend away playing in Red Rock Canyon (near Las Vegas), only Lynne has been making progress at F8. She finished up the painting of the wall color, leaving only the trim and door to finish.

    Following a meeting with the helpful person at the county health department, we are learning about some of the additional things we will need to do before opening. The two big items being the inclusion of a hand (only) wash sink and sealing of the floors.

    Our federal brewer's permit is making progress on being approved and so we will hopefully be able to move on to applying for our state permit soon. These permits are likely to be the controlling factor in terms of when we can open our doors.

    In the mean time, I captured these two views while at Red Rock Canyon...




    12 November 2009 - Being away for work for a couple of days put a slight delay in my efforts, but we have still made some progress this week. Lynne has now started to put color onto the retail space walls. This is obviously quite exciting for her as she has chosen to work on this over playing in her sunny yard.

    Also, the glycol chiller is now fully functional and simply requries the insulation of the bulk tank and plumbing in order to limit the heat loss from the system.

    Next on the list is plumbing the freon lines of the cellar's refrigeration system.


    9 November 2009 - A quick update from on the road in LA where I've been working for the past couple of days. I'm happy to say that it's been a great trip. I was able to get together my friend Cheryl who we used to have the pleasure of seeing regularly at EAC in Chicago, until she moved to California a couple of years ago. She drove up to meet me at LAX and we had a nice dinner and caught up.

    Work was good too, meeting with my friend/boss Mark, doing some brainstorming on my next project. We have many similar interests (pinball, mechanical stuff, etc.) and it is always great to bounce ideas off each other about things we are each doing.

    A short trip, I'll be heading home in the morning and my wonderful wife will be picking me up at Midway on our way to go climbing together at EAC...

    8 November 2009 - On Saturday morning, both my dad and Shaun showed up to help out. Our project for the day was to finish installing the steam vent for the brew kettle. This included some welding of stainless steel, which went very well. Shaun has been storing his MIG welder at F8 since he began helping there and I bought a tank of Stargon and some wire to allow us to weld some stainless (there are a number of small stainless welding projects queued). Shaun hasn't actually done a whole bunch of stainless MIG work, being primarily a stick welder, but he adapted quickly, putting my initial attempts to shame.

    While we were working on the steam vent, Lynne busied herself with putting on the 2nd coat of primer on the retail space walls. It was a big tradeoff for her as she was torn between wanting to paint and wanting to be outside, the weather being spectacularly warm and sunny. The walls are now primed and waiting for some color, which I think she is the most excited to start.

    After we finished with the steam vent, Shaun was willing to try his hand at welding a ferrule to the bottom of the old 1/2 BBL keg that I plan on using for a grant vessel. After Shaun ran a beautiful bead around the ferrule, I ground and pollished it and it turned out perfect.

    This morning, after a couple of days of pumping a vacuum in the freon system for the glycol chiller and leaving it sealed overnight to verify that it did not leak, I released the R22 freon into the system and tested it. As the reported temperature reached 32 F, I decided it best to pour in five gallons of food grade glycol to ensure that the water did not freeze. This is a momentous occasion for me as I've been nervous about my Franekstein approach to saving money on the glycol chiller, but it would seem that I've made the correct choice.



    6 November 2009 (addendum) - Using a suggestion on how to find the leak in the freon plumbing from a good friend who has done plenty of this kind of work, I found the leak and fixed it in about 20 minutes, so I guess it wasn't as bad as I was thinking it mignt be. After the repair, I left the vacuum pump running for a few hours and it pulled down to about 35 microns. Now it will sit over night to make sure that the vacuum holds and to convince me that there are no more leaks.

    Lynne finished the first coat of primer on her walls and I made a small oak "counter" to fit onto the top edge of the dutch door.

    Tomorrow morning, my dad and Shaun are both coming to help finish installing the steam vent for the kettle.

    Life is good...

    6 November 2009 - This week's evening activities have been busy with me working on a few smaller items as well as hooking up the freon plumbing for the glycol chiller. Lynne began work on painting the retail space by cutting in the primer and is excited to be beginning the painting instead of the drywall and prep work.

    The smaller items included assembling some stainless steel fittings to make up the oxygenator with sight glass and temerature gauge, the mounting of the secondary CO2 regulators for the brite tanks, and creating a dutch door out of the insulated steel clad exterior door that separates the retail and production spaces.

    The oxygenation occurs as the last step when the wort is transferred from the brew kettle through a heat exchanger (to bring the liquid down to room temperature) and into the fermentor. The sight glass lets me see the amount of oxygen being injected and the oxygen helps the fermentation get off to a good start.

    The secondary CO2 regulators will be fed from a bulk CO2 tank and will feed carbonation stones in each of the large conditioning "brite" tanks. This process allows each brew to be adjusted for just the right amount of bubbles and also provides pressure to later serve the beer through the on premise taps, the back of which are showing below the regulators.

    The dutch door was a PITA as the local hardware store did not have a circular saw which was rated to cut both metal and wood. So I bought a cheap carbide blade knowing that it would be dead after cutting the door in half. This door is one from a previous project that had never been used. The idea behind the dutch door is to maintain the separation between the all ages retail space and the 21 and over production space. As can be seen in the first picture, the door is now hanging in two halves. I still need to add a nice small counter like surface to the top of the bottom half.

    The freon lines are now run and brazed, but there appears to be a small leak that needs to be tracked down before the R22 can be added. Why can't these things just work the first time? Sigh...



    1 November 2009 - Another month has come and gone, with the end of October being very busy, beginning with a Halloween party on Friday evening. Our friend Cameron came to town from Evanston for the event and went as Banana in Pajamas. Lynne dressed as a sexy Octoberfest girl, and I was a hops god.

    Saturday, I did some more work on the glycol chiller system and then my dad stopped by to help, so we worked on installing the brew kettle's steam vent. In the afternoon, my friends Shaun and Mike and I went to see Bob Dylan in concert at the Aragon ballroom in Chicago. Bob is 68 now and still puts on a great show. On the way home from the concert, we stopped at Brickworks and had a good time sampling their latest brews and talking to Tom and Brandon.

    Completing the circulation system of the glycol chiller was my top priority for this weekend and I was able to finish this on Sunday. The chiller began life as standalone Thermal Care Accuchiller used for industrial process. I bought it used on eBay and gutted it for use in our system. The original condensing unit and pump were 3 phase 408 volt, but we only have single phase power and I wanted to split the condenser from the heat exchanger to move the heat outside of the building. To this end, I mounted a new single phase 220 volt condenser unit on the outside of the building and found a new single phase pump on eBay. Once the circulation plumbing was completed, I filled the reservoir about half full and turned on the pump to find out if there were any leaks. The system self primed and purged the air and worked flawlessly. The next step will be to install the line set between the condenser and the chiller's heat exchanger, allowing the system to cool fermenters.





    30 October 2009 - Another month has nearly gone by. The web site passed the 1000 hits mark this week, which is pretty impressive given that the counter tracks unique IP (internet) addresses. I'm excited that all of this interest will turn into people coming to visit and try our beer when we finally open...

    Not much to report pictorially this week. I've been working on finishing the glycol chiller system and hope to have more to report on that front after this weekend. Until then, I sincerely hope that everyone has a wonderful Halloween - BOOO!!!

    27 October 2009 - On Monday, our last day at The Red, I decided that we needed to maximize the short time remaining by allowing everyone to do some things in their range. The best place I know for this is of course Muir Valley's Bruise Brother's Wall. I cannot easily count the number of times that I've been to this wall, but it is still always a good time. Usually Bruise Brothers is a busy wall as it has such a mix of easy to moderate sport routes, but being Monday, we were in luck and there was only one other group there when we arrived.

    Bob continued to amaze me this trip by stepping up to lead most of the routes this day. We began on the upper tier by setting up one rope between CH4 and A-Beano, then a second rope on The Offering. While we were taking turns on these routes, Ailie, who had been hoping to do so all trip, took the opportunity to cut Joel's hair, and Bob the avid photographer captured the moment.

    The other group at Bruise Brother's, four French speaking guys, were working on the harder routes to our left and at one point they wanted to stick clip the first bolt of Jungle Trundler, but could not quite reach in the usual fashion. Fortunately climbers tend to be creative and I captured their effort on my iPhone.

    As we were finishing up on the upper tier routes, before taking down the rope from CH4, I decided to attempt the roof route above CH4 called Rising. I had been eyeing it for a number of trips and even helped Rick Weber install a glue-in bolt under the roof by belaying him as he did so a few trips back. The route was difficult (5.11a) as roofs tend to be, and as expected, hence my trepidation. Jumping on cold, I did hang once after attempting the second move over the roof, but then after a quick rest pushed through to the top. A sweet climb - next time I'll send it!

    Moving to the lower tier, Bob led Send Me On My Way and all interested parties took their turn. Aim did especially well, overcoming her demons at the start, and making it all the way to the top. We were fighting time as Ailie wanted to be home sooner rather than later, but we ended up doing one more route, Rat Stew, which was Bob's most difficult lead to date as he broke into the 5.10 range - nice job Bob!

    Our route list for the day was:

  • CH4 5.8- **
  • A-Beano 5.7 **
  • The Offering 5.7 ***
  • Rising 5.11a ***
  • Send Me On My Way 5.9- ****
  • Rat Stew 5.10a ****

    As we were winding up, I captured this photo of Lynne, looking F.I.N.E., standing in the sun in the top which our friend Katy bought for her. Lynne asked me to take the picture so that Katy could see it on her...

    As we arrived back at the Muir Valley parking lot, Lynne spotted a praying mantis on the hood of one of the cars. Always a good omen, these ancient creatures never cease to capture my attention.

    I want to say that Aim and Ailie both seemed to have a great time and did quite well on their first trip to the outdoors climbing world. Bob both cimbed and led very well. Lynne zoomed up some difficult routes in good fashion, and Joel made me proud too, going to the top of some pretty high and exposed routes. Nicely done all!

    Following a relaxed dinner at Miguel's, the trip home was uneventful and went by quickly as Lynne read "The Fellowship of The Ring" to Joel and me as I drove.

    Today is the start of a new albeit short week and while our trips are always fun, it is good to be home and back at the F8 project...stay tuned!




  • 25 October 2009 - Today we attempted to avoid the crowds and introduce Aim and Ailie to something new. This was accomplished by heading to Pebble Beach where we did some trad (vs. sport) climbing and all sat atop a nice pinnacle called Arrowhead. The top of this climb was just large enough for the six of us without anyone falling off and to take this first self portrait.

    Bob led Scabies, which is his most difficult lead climb yet. He is progressing quite well in his climbing skills. I put up a rope on Envrionmental Impact, a classic crack climb. Another group had a rope on Straightedge, and so I had the opportunity to climb a 12a without leading it, what a blast!

    Our route list for the day was:

  • The Arrowhead 5.7 ***
  • Scabies 5.9+ ***
  • Enviromental Impact 5.7 ****
  • Straightedge 5.12a ***

    At lunch, we had tortillas with banana and honey and Lynne's excellent banana bread, which Ailie ate with banana on top.

    The last pics are of Aim belaying and the hand carved door at Miguel's, where we had some welcome pizza in the cool/crisp air of the early evening.

    Tomorrow we are thinking about Bruise Brother's wall at Muir Valley before heading home...





  • 24 October 2009 - While the weather was not as good as we hoped it might be today, there was only a light mist and the temerature was chilly. Many of us brought our thermals, so those along with our layers, hats, and gloves kept us warm. The sun kept trying to come out and it succeeded a couple of times, primarily near the end of the day. We are hoping that this is a sign that tomorrow's weather will be nicer. The current forecast is for mid 60s and sunny, so we are psyched!

    Today is the first time that Aim and Ailie have ever climbed outdoors and as such we broke them in at Muir Valley's Practice Wall. We worked a number of routes, Bob and I taking turns on leads, then Lynne led the final route of the day, a 5.6 chimney called Dragon's Mouth. In order, they were:

  • Ai Bang Mai Fa Kin Ni 5.7 ** (Bob's lead)
  • Mercenary of the Mandarin Chicken 5.9+ *** (Tom's lead)
  • Beta Spewer 5.10b *** (Tom's lead)
  • Acrophobiacs Anonymous 5.4 ** Tom's lead)
  • Yu Stin Ki Pu 5.6 ** (Tom & Bob's lead)
  • Kate's 1st Trad Lead 5.1 ** (Tom only, free solo)
  • Low Exposure 5.8 ** (Tom & Bob's lead)
  • Crescent Moon 5.9+ *** (Tom's lead)
  • Crescendo 5.8+ ** (Bob's lead)
  • Dragon's Mouth 5.6 ** (Lynne's lead)

    Some of us had been to Practice wall before, but this was the first time we had covered as many routes as this.

    After climbing, we returned to TNI for beer, cheese, dinner, and general revelry. Everyone was in good spirits and I was happy to see that TNI had lots of patrons. We worry that the new ownership along with the downturn in economic times might spell the end of the hostel, but fortunately this doesn't appear to be the case.

    As everyone tends to bring a variety of foods and drinks to these climbing trips, Bob bought a Three Floyd's Dreadnaught, which he had not had prior to this trip. He was in for a treat and the picture shows his response!

  • 23 October 2009 - This is our long weekend at Red River Gorge in Kentucky (The Red :-). Our drive down was filled with volumes of rain as can be seen in the first picture, in Florance Kentucky. Fortunately the rain stopped just as we were about 15 miles from our destination. The sun kept trying to come out and after dropping off some stuff at True North Inn (TNI), we headed to Roadside for a quick approach to some climbing. We walked past a huge group of people standing in line at the 10 wall, past a couple of poeple working on Ro-Sham-Po, saying that it was wet (Is that possible?), back to the 8 wall, which was surprisingly devoid of people. The wall was wet, but we had some fun on C Sharp B Flat, and the skies turned blue as the picture testifies.

    As there was a wedding rehearsal dinner at TNI the restaurant was closed for the evening and so we next headed to Miguel's Pizza for dinner, planning to return to TNI before all of the parking was taken.

    The original plan was that nine other friends were going to join us here in The Red, but so far, four have bailed, two due to rain forecasts, one for a family emergency, and the forth was left without a ride because of the third. Three of the nine just messaged that they are an hour away, and the last two are currently planning on heading down tomorrow. I hope they decide to come. The Red is always a fun time and it is especially fun when spent with our friends....



    22 October 2009 - This has been a busy week of morning/evening work at F8 around my day job. Feeling the need to delegate, I broke down and hired G.L. Jorgensen Heating & Cooling to install a spiral duct to distribute the heat and A/C within F8. While I'm certain that I could have undertaken this job, there just aren't enough spare hours in the day to do everything myself. Also, I've had Jorgensen do work for me before and I like to support them.

    A while ago, I put in an offer to purchase a well used IDD Mini King keg washer and filling machine from a brewery in California which had closed its doors a while ago and declared bankruptcy. My dealings were through Sound Brewing and the lawyers who were handling the bankruptcy. A number of months went by after my check had been sent and finally the offer was accepted, generating the paperwork which allowed me to finalize the purchase. It wasn't until this point that I discovered that the machine was located in the old brewery building which had been effectively vacated and so whereas normally when you want to ship some equipment, there is someone there to place the machine onto a pallet and load it into a truck, this wasn't the case. Fortunately, there was one other piece of equipment left at the location and a rigging company had been hired to load it for the buyer. I was able to arrange to have this company load my machine onto their truck and take it back to their shop so as to avoid having to arrange to have someone open the old brewery again and to hire another rigging company to do the work - an expensive proposition.

    To make this already long story shorter, the machine arrived this week and while it is going to require a fair amount of effort to clean it up and make it serviceable, it looks to be a great time saver and a reasonable deal.

    Looking at the machine, complete with all of the well worn work surfaces, labels from previous breweries, etc. I cannot help but wonder what stories it could tell about the horrendous trube it had washed from returned kegs, the spectacular beers that it had then filled into those kegs, the people who had toiled to produce those beers, how many of those breweries are still running and how many have failed or simply retired...

    Finally, this week's project for me has been to finish the water plumbing. This included installing a pair of large GE GXWH40L filter units in series, one with a particle filter and the next with a carbon filter, then feeding a four outlet manifold. The entire system is plumbed in 1 inch copper pipe so as to provide the best flow rate possible, minimizing the time it takes to fill the kettle with 240 gallons of water...

    After installing the filter units, when I removed the bottoms in order to install the filters, I discovered that one of the O-rings had been damaged when assembled at the factory by catching the O-ring in the threads. When I returned to Home Depot for a replacement O-ring, the plumbing guy proceeded to open a similar filter from off of the shelf in order to give me its O-ring. His response to my surprise was to tell me that the unit which donated the replacement filter would become garbage. I don't understand how our country has devolved to the state where instead of stocking a $0.50 replacement part, they cannibalize a perfectly good $56 unit and take the loss. Unbelievable!



    19 October 2009 - Saturday, Lynne, Joel, and I drove in to Chicago together to spend the day at Pinball Expo. We played lots of games and talked to a number of friends, enjoying our afternoon inside and out of the cold damp weather. After Pinball Expo was over (for us), we enjoyed dining with Cameron, Bill, Carter, and Merrillee. Carter is just 3 years old and was a pleasure to have with us as he is a remarkably well behaved and happy fellow.

    Spending as much time as I did at Pinball Expo this past week was hard, knowing that I could have been accomplishing something at F8. Fortunately Lynne pressed on with her work on the retail space drywall and the break was good for me. Seeing all of my pinball friends was well worth any delays...

    Sunday we did the final push to finish with the FRP in the cellar. This was nearly all that is left to be done in the cellar except for some trim on the inside and then positioning and hooking up the equipment. Completing the FRP also helped free up some space, which will be good as the keg washer/filler is due to arrive soon.

    Lynne finished the drywall and is eager to start painting the retail space. The primer and paint were sitting, awaiting her attention while we busied ourselves with the FRP, and while she would have preferred to paint, she understood my desire to have the FRP behind us.

    Lynne has been very supportive as well as a great help durring this entire process - thanks sweetie!




    15 October 2009 - I had been resisting the extra work involved, but my friend Bill's suggestion to add links to larger pictures pushed me over the edge. So for all new pictures, you will be able to click on the small image in order to see a larger image.

    This week is a bit crazier than usual as Pinball Expo 2009 is happening and my pinball roots are pretty deep. I've been fortunate to have a number of jobs over the years which were truly fun. Designing pinball games for Williams Electronics Games from 1993 until their demise in 1999 was of those jobs. The people I worked with were incredibly good and talented and I continue to enjoy seeing those who attend Pinball Expo.

    Unfortunately, my friend Mark who was going to attend Expo this year (and come see our progress at F8 in person), was unable to make it after all, but I am looking forward to him visiting at a later date, perhaps after we are actually up and running...

    At the moment, I have to hurry and push these changes to the server so that I can leave to make the long drive in and play Whirlyball with my pinball friends:-)


    12 October 2009 - Tonight saw some exciting progress, at least from my viewpoint. After having all of this equipment sit around for what seems like forever, without any of it doing anything it is supposed to do, I hooked up the final electrical connections to the brew kettle, capped the various pipe/tri-clamp exits, and filled the kettle with water until the level sensor was covered, about 110 gallons. At this point, with the set temperature at 80 F and the water at 60 F, I pushed the "Burner" button and listened as the 200,000 BTU gas burner's blower fan kicked in, followed a short time later by the sound of the electronic ignition, and finally the whump of the gas turning to flames. Woot! Then after a few more minutes, as I watched the water temperature indicator rise to the 80 F set point, the burner turned off. Double WOOT!
    11 October 2009 - Another week has flown by and we've made some good progress, although most of it does not lend itself to being highly visible, so no new pictures. Instead I took this one of the trees turning color. Fall is definitely here. We turned on our furnace yesterday and last night we had our first hard freeze.

    During evenings this week, I mounted the pump for the glycol system on a cement pad under the stairs and installed the exhaust vent for the kettle. The steam vent will be the next piece of that puzzle.

    After an evening of work at F8, Lynne and I enjoyed a dinner and some fine beer at Brickworks. Unfortunately we missed seeing Tom as I would have liked to chat with him and congradulate him on his success - the place was booming with business. I also wanted to tell him in person how outstanding his Dunkelweizen is.

    Saturday, Lynne continued to sand the drywall and then switched to painting the cellar door trim while I worked on the glycol plumbing and electrical conduit.

    We have most of today off as we are heading into Chicago to help our friend Ailie celebrate both her birthday and having run in the Chicago marathon - happy birthday Ailie!

    5 October 2009 (part two) - Lynne and I returned this evening to do some more work. Lynne busied herself sanding drywall and I continued to install the glycol circulation system which now makes its way around the entire production area. The chiller will live under the stairs and supply the chilled water/glycol solution to the jacketed fermentation tanks.Once the pipe is installed, it will be insulated.

    It's been a while since I included a picture of the production area from this view. The tanks are mostly now all in place, the FRP is on the walls, the glycol pipes run along the top of the walls, and the grain mill is on the 2nd floor above the cellar.

    Lynne and Annabelle spent some time today looking at paint colors for the retail space. After the mudding/sanding cycle is completed, the drywall will be primed, painted, and made ready for the public.


    5 October 2009 - Where did Septermber go? I cannot believe that it is October already. I need to brew some beer soon or I'm going to go crazy!

    I realize that it has been a few days since my last update, and we've made some good progress in that time. The drywal is mudded, taped, and the first pass of sanding is done. The cellar FRP is nearly complete, and the glycol system plumbing has been started.

    There is still plenty to be done and I'll take some new pictures soon.

    30 September 2009 - On Tuesday, Lynne and Annabelle picked up a load of drywall and delivered it to F8. Annabelle's dad was in town, so he went along to supervise and to have a chance to see the brewery. Apparently drywall goes up much faster than FRP as over the past two evenings, we managed to hang the entire lot of 16 sheets. Then to top it off, we also hung the door between the retail space and the production area.

    While I was working this evening, my old friend Garrett stopped by to see our progress. I had not seen him in a while and it was fun to chat and show him around. Apparently it was the evening for guests as another fellow stopped by on his bicycle to see how we were doing and lastly, I received an email from another Valparaiso beer aficianado who is excited about our opening. It would seem that word is traveling fast and we are starting to get a buzz going.

    It needs to be noted that yesterday was Shaun's birthday and while I failed to make it to Pat's Liquors in Porter today to pick up the keg of Three Floyd's Alpha King I ordered for him, I will do so tomorrow...

    I sincerely hope that Shaun had a most excellent birthday!



    28 September 2009 - Over this past weekend, I installed the lighting in the cellar and began arranging the equipment in the production space. Having the lights in the cellar means that we no longer have to use the light of the hot halogen work lamp.

    It was fun to actually play with the equipment for a while, positioning, leveling, hooking up the natural gas line to the brew kettle, etc. Also, now that the mash tun is in place, we can begin work on the platform between it and the brew kettle.

    The actual construction portion of the project is coming to a close. Last Friday, I had the city building inspector come by to give us the OK to enclose the wall in the retail space with drywall and last night Lynne and I put up the first of the final sheets of FRP on the wall in the cellar.

    25 September 2009 - Last night was stellar, in my world anyway. Lynne and I began with the intent to put up a couple more ceiling sheets of FRP in the cellar and as we were getting started, Lynne's symbiant Annabelle called to say she was coming over to help. Moments later the three of us were putting up FRP like there was no tomorrow. Anne had to leave about an hour before Lynne and I, but by the end of the evening, the ceiling was finished and I was excited to finally be able to mount the cellar's refrigeration evaporator.

    Our next and final FRP work will be to complete the walls of the cellar. As compared to installing FRP on the ceiling, the walls will be a cake walk.

    23 September 2009 - It came to my attention that some of the graphics on this web site have not been working properly. After investigating further, it seems that Internet Exporer does not support JPG format with alpha channel. All of the images which were having problems have now been changed to be GIF format and as such should display properly. If there are still problems, please let me know...

    In brewery news, our low end single station bottle filler and crowner arrived yesterday and will require some maintenance before it is ready to use, but should get us started.

    22 September 2009 - Woot! The hit counter on our web site has moved past the 500 mark :-)

    Yesterday, Lynne and Joel helped me install two more sheets of FRP onto the cellar's ceiling. The first did not go very smoothly, but we figured out a new technique for the second and so the rest (five more) should not be too bad. Still, working over our heads is more difficult...

    I had been trying to decide upon a used deilvery vehicle. The choice was either a Ford E-150 work van or a larger Chevy/Grumman step van. In the end I chose the work van. While it doesn't have as much of the cool factor or uniqueness that the step van would have, it will be easier to drive, maintain, and more economical on fuel.

    20 September 2009 - This weekend was busy, but not entirely with work at F8. We attended the beautiful wedding of our friends Justin and Wendi at the Michigan City beach, followed with a reception later in the afternoon. This along with Joel's soccer on Saturday and Joel and my soccer today (during which Joel scored three goals :-), the business of constructing a brewery languished. Still we did manage to finish putting up the FRP in the main production area and begin putting it up onto the ceiling of the cellar.

    While we were working at F8 this morning, Bob Ostrander of IndianaBeer.com stopped by to see what we were up to and we had a nice time talking about all of the great craft breweries which are located in Indiana.


    17 September 2009 - This has been a busy week with some good progress in the past couple of days. We now have FRP most of the way around the main production area, and once the last couple of sheets go up there, it will be time to tackle the inside of the cellar. The ceiling of the cellar will likely be the most difficult part of that portion of the project.

    The last two fermenters arrived on Tuesday and look good. They are used and are the lidded open top variety, 10 hectoliters each. Having four fermenters will give us the ability to be brewing more often and to have more variety. While the open style fermenter is more work to clean, I'm hoping that the variety of types will give me the ability to craft some classic ales.

    As construction in the main production area is completed, we will be able to move each of the tanks into their final positions and install the electical, gas, and glycol plumbing as necessary for the various components. Once this step is completed, I can also begin cleaning and testing everything.

    Very exciting!

    13 September 2009 - We finished our primary goals this weekend, which was to ready the inside of the cellar and the production area walls for Fiberglass Reinforced Panels. So our next big effort will be to glue up the FRP, which will be all kinds of excitment when doing so on the ceiling of the cellar.

    Following Shaun's completion of the welding of the small double tank stand, Lynne has preped the metal frame for more POR-15 paint and plans to finish that this week.

    As part of working on the cellar, I mounted a six handle draft setup on the outside wall of the cellar with the shanks going through the cellar wall. These will either be fed directly from the brite tanks or from kegs.

    The final two fermenters are due to arrive on Tuesday and our space is a bit tight with our trying to maintain enough room for the construction, so I moved the grain mill up above the cellar, which is where I've been planning on it living. The grains will be crushed there and flow down into the mash tun through a large PVC pipe and hydrator.

    While the list of things left to do is still way too long to enumerate, the major items are:

  • hang the FRP
  • construct the stair and mezzanine level railings
  • install the glycol chiller and plumbing
  • install the cellar refrigeration system
  • position all of the tanks and hook those which are cooled to the glycol
  • install the water filtration system
  • install the brew kettle
  • BREW SOME TASTY BEER :-)
  • 11 September 2009 - This has been a busy week and I've been negligent of F8, climbing with friends at the Chicago gyms we frequent both Tueday and Thursday evenings. Keeping up with my climbing workouts has paid off as I was able to send the 5.11 projects at both EAC and LPAC :-)

    On Wednesday, my friend Tim dropped by for a visit while he was in the area for work and it was excellent to see him. Also, Joel had his braces removed and Tim took this excellent picture of us.

    Shaun had a few days off from his day job and came in to weld up the tank stand he created for a pair of 150 gallon tanks which I purchased a while back that did not have legs.

    My minimal accomplishments since last reported have been to purchase some used office furniture and to insulate the cellar door.

    This weekend promises to be busy with lots of work at F8, hopefully getting a good start on finishing the sheeting inside of the cellar as well as the plywood inside of the production area.

    A newspaper article this week reported that our friends at nearby Brickwork's Brewing opened to a full house - congrats!



    8 September 2009 - Monday my family and my parents did our annual Labor Day Hesston steam/gas engine show trip, taking my dad's 1906 2HP International gasoline engine. The process consists of getting to my parent's house around 8a, loading up the engine onto his trailer as pulled behind Lynne's Tahoe. Then we head back through town and pick up Lynne and Joel (this gives them some extra time to get going in the morning as they are more inclined to sleeping in :-). Drive about 45 minutes NE to the show grounds and unload. The weather was very pleasant this year, unlike some times when it is blazingly hot. We found a nice shady location to setup, which was nice as well. We spent the day watching the engine run, strolling through the flee markets, checking out the other gasoline engines, steam engines, and tractors, eating (elephant ear, rib eye sandwich, popcorn, etc.), road the steam train (the small one this year), then sat a while longer before loading up and heading home to unload again. Not a long day, but very nice!

    Once home, I had a couple of hours to work on the cellar door before Cameron and Matt stopped by on their way back to Chicago from Indiana Beach. They wanted to see the progress at F8 and it was fun giving them the tour before we went in search of dinner.

    The cellar door is now hung and I'm quite happy with it. All that is left is to install the insulation and sheet it (along with the rest of the cellar and room) with FRP. The two blocks are temporary handles until I install the real one. Joel wondered if it was dark in the cellar with the door closed and so we did the experiment -- pretty dark...



    6 September 2009 - I spent all of Saturday morning replacing all of the old dried/cracked/broken wiring on the forklift and then drove it out to F8 around 3p. I had Shaun follow me in his car for safety. Unfortunately the drive behind the building is gravel and has not been rolled or compacted since many things have been done in my area, so the fork had a tendency to sink. I ended up having to put down some OSB to get it into the building. I'll have to talk to Todd next week. Ideally, the rear drive would be paved.

    After the forklift, I installed our sign onto the front of the building and am quite happy with the way that it turned out. Many thanks to Lynne for all of her effort in applying the many coats of paint.

    The remainder of Saturday and Sunday morning were spent installing more insulation in the cellar. All of the walls are now finished and the ceiling has one more layer of two inch pink foam board to go. After a break for lunch, a Menards run for more materials, mowing the yard at home (it has been about 4 weeks), and soccer (scored two goals :-), I returned to F8 and began working on the cellar door. The next step is to hang the door on the hinges to see how it swings, then add the instulation and sheeting.

    All in all a fairly productive weekend so far. Tomorrow is our annual family trip to the Hesston Live Steam Show -- should be a nice day!


    4 September 2009 - It's been a couple of days and so here is the latest update. Not much has happened in terms of construction since my last post. I've been busy with my paying job, life, climbing, and all.

    We did have NIPSCO come out to set the gas meter, so we now have heat and hot water. Amazingly, there are no new NIPSCO stories from this event to tell.

    While eating lunch downtown at Isabella Bean's on Wednesday, I noticed one of Justin Vining's works on wood which I had not taken in on the evening of my brother Jon's opening (as mentioned in the 31 August entry below). I love the whimsical feel and thinking that the piece would look great on the wall in my new office at F8 and wanting to support a local artist and climber, I purchased it.


    The painting is called "From the 1850s" and is described by Justin as follows:

    "A bit of background that you may find interesting if I did not already mention it, is that this I obtained this particular piece of wood from my boss at the firm who grew up in Iowa. Sometime when he was younger they dismantled a family barn that was built in the 1850's and this particular piece of wood was from the center one of the barn doors as you can see the nail holes in an angle pattern going right through the middle of the board. Also, the board was rough cut and to prep the surface for painting I sanded it fairly smooth, however as you can tell it is still pretty rough. A bit about the paint, I used transparent acrylics to let the natural color of the wood shine through the paint to try and unify it. To further accomplish this look one the painting was finished I used a water based stain over the whole thing and then three layers of a gloss polycrylic." - Justin Vining

    There is also news on the forklift story. I stripped the paint from the name tag and although it is barely legible, I was able to determine the model and serial numbers and with those discover that while the Clark Car Loader was in production from 1939 - 1964, mine is a 1954. I ordered both the service and the parts manuals and so while many parts are likely no longer available, working on the machine will be easier.

    Yesterday was beautiful and after working inside at my computer all day, I was inspired to be outside so I road my VFR into the city and climbed at the outdoor wall at Lincoln Park Athletic Club (LPAC) for a couple of hours. I always enjoy seeing the sunset to the west and the city skyline to the east from the top of the 70' wall. Finally, the nearly full moon accompanied me on my ride home.

    1 September 2009 - Yikes! Is it really September?

    I did about 3 hours of solo work at F8 last night, working on insulating the inside of the cellar and finished about 1/3 of the ceiling. There is still a lot to go, but progress is steady.

    The picture is of the Clark forklift. I took the forks off for the moment, but you can see that this is a pretty compact machine for its age. Hopefully, once I remove the paint from the name plate, the model number and actual vintage of the machine will be revealed. I'm guessing that it was built in the WWII era.

    In other news, I secured a nice pair of jacketed open top fermenters, complementing the two conical unitank fermenters we already have, filling our remaining production space, and rounding out our system nicely for the foreseeable future.

    31 August 2009 - The weekend began Friday evening with work on a number of things which are not visible and yet took a fair amount of time to accomplish, primarily the furnace and the alarm system. Both are now done. We finished early Friday night in order to attend a new showing of my brother Jon's and his wife Brenda's art at Isabella Bean Coffee House, Cafe, & Gallery. Brenda is an art teacher and has not been actively displaying/selling her works, so it was fun to see them on display in the gallery. Jon has been painting full time for the past couple of years and his works can be seen at a couple of galleries and on his web site, The Art of Jon Uban.

    The gallery portion of the coffee house is new and the opening was well attended and very nice with an excellent display of art from five artists. While there, Joel was wearing his Miguel's Pizza shirt from The Red and one of the other artists, Justin Vining, stopped to talk to us because he recognized it. As it turns out, we had met him before at another local coffee shop which is no longer in business. Justin is also a climber and spent a great deal of time at The Red and dated Miguel's daughter. It was fun meeting and talking to another climber in Valpo.

    Following the showing, we joined Jon and Brenda for a wonderful dinner at the local Spanish restaurant, Don Quijote. While waiting for dinner to be served, Joel and I were goofing around and I messed up his hair and took this picture. I think it's great and my neighbor Mike pointed out that it looks like a young Bob Dylan :-)

    On Saturday, we continued to do some work in the morning and then took a break to go look at an old Clark forklift which my neighbor Mike's family had for sale, followed by a trip to see the progress at Tom Coster Jr.'s Brickworks Brewing Company in Hobart. Brickworks is a full on brewpub in a 7000 square foot space, making our operation feel tiny by comparison. Tom's system was made and installed by the same people who made our brew kettle and fermenters, Premier Stainless. Tom looks quite happy standing in front of his long line of brewing equipment.

    On Sunday, following our ritual breakfast of homemade waffles, we returned to F8 to put up some of the plywood which will line the entire production area, giving a solid backing to the fiberglass reinforced panels (FRP) that will go over the plywood. Progress on this front continued until about 2p when we had arranged to pick up the forklift with the help of Shaun's friend Chris who has a very nice Duramax truck/trailer setup. Thanks much to Chris (and Shaun) for their help getting the forklift to my house. Details and pics of the forklift will follow in a future report as I find time to perform the necessary maintenance on it.

    Joel and I usually play soccer on Sunday afternoons and fortunately we finished up with the forklift in time to join in the second half of play. The weather was perfect as the fall temps are already beginning to arrive and as compared with only a couple of weeks earlier, the cool air made it feel like you could run forever...



    27 August 2009 - We purchased 64 new 1/2 barrel kegs from Buzzard's Bay Brewing in Massachusetts a while ago and they had been holding them for us until we had room for them. We decided that the time had come and they arrived yesterday stacked high on three pallets. It was good exercise hauling them one at a time to the upper level. Buzzard's Bay had ordered a container from over seas in order to get a better price but did not need the entire lot, so we were able to get a pretty good deal on them. The only issue is that we have to cover over the embossed Bussard's Bay name before we can use them. I'll talk more about this in the future when I implement my solution. As we are still working on the buildout of the main floor, having just finished enough of the storage/office area, we decided to store the kegs there until we are ready for them. They make a convenient baracade to keep anyone from walking off of the mezzanine level before the railing is up...

    Last night, after moving the kegs, I continued to install the furnace and A/C unit while Lynne finished assembling the sign, with the exception of the "8 rope" which will entwine the large "F". The sign turned out beautiful, but I'm a bit disappointed at how two dimensional it looks from a distance after putting all of the work into cutting the letters out, etc. Perhaps a simple flat painted sign would be been just as good.


    26 August 2009 - It's been a few days since my last update. After returning from work in LA, we spent a fair amount of the remaining weekend as well as additional free time this week making progress on the F8 buildout. I insulated the outside of the cellar and Shaun helped me install the outer vapor barrier and finish installing the staircase. This allowed us to install the "office" floor, adding a significant amount of room to our space. The office will only consume a small portion of the elevated area, the remainder to be used for grain processing and storage. The current plan is to keep the office/storage area open with only a guard rail around the perimeter.

    Todd (one of the building owners) dropped off the furnace and mounted the A/C condensing unit onto the outside of the building, which allowed me to begin the installation of the pair. I will hopefully have those finished by this evening, which will be nice as working in the hot and humid building takes away from the fun. I still have to decide about how to run the duct work for the room.

    Lynne has finished her painting of the letters for the sign and I have to say that she did an excellent job and that the sign looks fabulous.



    22 August 2009 - My work in LA is complete for now and I was up early in order to be at LAX for my flight home. I am presently sitting at gate one of the Southwest terminal waiting for time to pass so that I can be home to see my family and enjoy what the weekend brings...
    19 August 2009 - I'm in LA for the remainder of this week for work and so will be away from F8 until my return. Joel and I managed to cut the lumber for the staircase which leads to the space above the cellar before I had to fly out Tuesday evening. I still need to cut two more steps and finish the wall (along side the refrigerator) where the stairs will be attached before installing them, but as can be seen in the image, they are ready to go...
    17 August 2009 - After a short morning of climbing at Phantasia where we climbed Lord of the Flies (5.8) and Overlord (5.10b), we got into our cars and headed home, stopping at the Montgomery Inn near Cincinnati for an early dinner and a nice break in the drive. Adam was *ready* for his dinner to arrive and Molly's look is perfect! Following our BBQ feast, we continued to caravan until we reached the north side of Lafayette where Lynne, Joel, and I split off of I65 in Hexnut to head due north and Molly, Adam, and Bob continued on to Chicago in Molly's Subaru. The trip was a complete success and we are looking forward to going to The Red again in October...

    As we arrived in Valpo, Lynne made the brilliant suggestion that we stop by F8 to see the new tanks. Mark had managed their arrival perfectly and the custom brew kettle and two unitank conical fermenters were sitting in the room, wrapped in plastic, waiting for us to unwrap them. Now all I need to do is figure out how to move them around in the room in order to be able to finish the walls and then put them up onto their leg levelers in their final positions.

    Finally, a big thanks to Shaun for finishing the legs for the two small tanks we are stacking. They were sitting in the room, ready for paint.


    16 August 2009 - Climbing was good yesterday, although it was quite humid and warm. We first went to The Great Wall in Muir Valley, where there is a nice mix of sport routes from easy to hard. Our group climbed:
    La Escalada (5.6) - Led by Bob
    Legends of Limonite (5.8) - Led by Bob
    Dynabolt Gold (5.10a) - Led by me
    Edge-A-Sketch (5.11c) - Led by me
    Ohio Arts (5.12b) - Attempted lead by me

    Next we went to Animal Crackers in Muir Valley, which has a small set of slab climbs in the 8 range.
    Casey (5.8) - Led by Molly
    Harvey (5.8) - Led by Lynne
    Rikki Tikki Tavi (5.8) - Led by me

    Adam has only been climbing since May, with this being his third time outside and he is progressing quite well. Joel enjoyed himself, doing best on the harder routes. Lynne stepped right up when I suggested she lead Harvey and did a great job. Bob's skills are taking off like a rocket. He is onsighting 10s now and leading 8s! Molly continues to be consistently strong and smooth. While I feel as strong as ever, I need to work on my lead head a bit as I believe I could have succeeded at Ohio Arts if my brain would have let me...

    Today will be a short climbing day before heading back. I'm actually as excited about being home where I can see the new F8 tanks as I am about climbing, but it is still early in the morning and we are just placing our breakfast orders here at True North Inn.

    15 August 2009 - The news from Mark yesterday morning was that the unitank conical fermenters and the custom brew kettle from Premier Stainless, had been delivered successfully. The fermenters had been slightly larger than our overhead door and had to be tipped over to fit them into the room, but Mark had handled the unloading without any difficulties. Now I am having to wait patiently until our return before I am able to look at the beautiful new tanks. At least I am being distracted by climbing with our friends...

    On a sad note, we learned from some of our friends (Barry and JJ) here at True North Inn about the untimely demise of Craig Luebben, who had frequented The Red and set a number of routes here...RIP

    13 August 2009 - Reporting from True North Inn, our home away from home at The Red in Kentucky, where we are climbing this weekend. We drove down this afternoon and will be enjoying some much needed holiday with our friends Molly, Adam, and Bob.

    Five of the 7 BBL grundy tanks, formerly owned by San Diego Brewing Co. arrived a day early on Wednesday. This was very exciting both because the tanks are coming in and because it meant that we would be more likely to be able to leave for The Red without delay today.

    Chris and Karen from Graphic 22 came out today to apply the vinyl graphic onto the window which does not look into the building because the "cellar" is there. The graphic has our Harness Your F8 ™ tag line at the bottom and the rest looks like the window is filled with hops. It turned out very nice. Thanks again to the people at Graphic 22! Now we need to fininsh the main sign and put it up over the awning to help complete the storefront...



    12 August 2009 - On Tuesday, Mark the stainless steel welder returned to patch the tiny leak in the mash tun's manway door weld. The job went quickly and while we were filling the tank with water to test it, Mark noticed that a praying mantis had landed just inside our door and was watching us. I believe that this is a sign of good things to come and I carefully wrangled the insect into my hand and carried it out back to some bushes where it would be safe and not locked inside of our building.

    Many thanks to Mark for his time and expertise in welding...

    Also, I forgot to mention, and would like to thank our other Mark (Lynne's brother) for making a road trip to Ohio very early on Monday morning to pickup three of our tanks and a couple of pumps. So far, we now have a variety of four tanks on site and the rest are scheduled to be delivered on Thursday, bringing the total to twelve. I use the term "tank" loosely as while they are tank like in nature, they each serve different purposes. While the mash tun was being welded, I spent some time organizing our space in order to have a place to put all of the "tanks" ... so excited!

    11 August 2009 - Yesterday, Shaun's welder friend Mark came by to weld the manway into the end of the mash tun. He is an experienced stainless steel welder and it took him a couple of hours to do the job. The door is welded both inside and out and we had to rotate the tank a number of times to make welding easier. While he was working, Shaun and I finished framing the last wall. Then when the weld was ready to test, we filled the tank with water and looked for leaks. Unfortunately, we found one tiny leak and so Mark will return later today to fix it.
    10 August 2009 - All summer long, people have been saying how cold is has been for July in Indiana. Well it all changed this weekend with the more typical heat and humidity pouring in... Frankly, I was much happier with the "cold".

    Shaun continued his marathon on Saturday, finishing up the welding of the new mash tun tank stand, while I cut pieces of square tubing for him to work with. Once all the pieces were cut, I also cut out the opening for the new manway that will be welded into the end of the tank in order to allow the spent grains to be more easily removed. As we were finishing up for the day, Shaun's welding friend Mark came by to evaluate how hard of a job welding in the manway would be and after looking at it he signed up to come back Monday afternoon and do the welding. So my work was cut out for me on Sunday as I needed to grind and paint the new stand, allowing Shaun to weld it onto the tank before the manway is put into place. It is kind of like a jigsaw puzzle as if the manway were installed first, the stand would not be able to slide down onto the tank. This can be seen in the first picture for this entry.

    Satuday evening was Lynne and my 30th high school reunion, which turned out to be more fun than I had expected. It is interesting to see how people have or have not changed over the years and to talk to the handful of people that we actually knew (and who showed up) out of the 450 something classmates with which we graduated.

    On Sunday morning, I ground and painted the tank stand, then began putting up some of the 2" sheet insulation, nearly completing one and one-half walls of the cellar before moving on to framing out the front wall of the retail space (see the second picture for this entry.

    As I have failed at this point to provide an architectural plan, everyone is probably wondering what the "cellar" (also called a walk in cooler) and "retail space" are and how it all fits together. So now our architectural plan is located at the top of this page.

    While I was putting up insulation and framing the wall, Lynne finished up some painting, including a second coat of yellow trim on the large F. Lynne and I are displaying the finished F in the third picture for this entry.

    Finally, as the day was growing long and we were both getting tired, Lynne called me to the door to see the beautiful silver lined cloud out back of our building.




    7 August 2009 - A fair amount has happened in the past couple of days. We went to collect the old farmer's dairy tank which I had been planning on using for our mash tun. I had looked at it a number of times and knew that the outer mild steel covering was rusty, but figured we could clean it up and repaint it as the stainless steel inner tank was in excellent condition. Lynne's brother Mark dragged the tank out of its resting place so that we could load it onto a trailer and bring it to the building, allowing us a look at the bottom. I was shocked to discover that the metal was in much worse condition than expected, but we decided that because the tank itself was in good shape we would dig deeper and see what could be done.

    After getting the tank to the building (a big thanks to Mark for this one, and for his ingenuity in building a roller cart to set it on), Shaun and I began disassembling the outer skin. As we did not intend to use the cooling coils (which had collected water, frozen, and burst), we removed them as well as all of the outer metal shell. We then designed a steel frame, picked up materials, and setup shop. I only spent about half of the day this morning before I returned home to do some "real" work, but Shaun pushed through the entire day, continuing to stay after my return in the evening. Of course our bribe of pizza and beer didn't hurt, but together we managed to build the majority of the new framework which replaces the unibody outer shell and lifts the tank up to our desired operating height. Once the frame is complete, it will be coated with POR-15. While the tank is exposed, we will also install a manway to allow the spent grains to be easily removed. Finally, new insulation and an outer skin will be placed around the tank to help keep the contents at a constant temperature during mashing.

    Many thanks to Shaun's dedication, effort, and friendship, as well as all of the others who are helping us to build Figure Eight Brewing...

    It should also be noted that Lynne and I celebrated our 26th anniversary last night, taking the evening off and going out for a nice dinner.



    5 August 2009 - Last night, Lynne and I returned to work after dinner, Lynne putting color onto the sign letters while I started on the ceiling/floor for the cellar/office areas.
    4 August 2009 - Check out our new Downloads button to the left to find some cool artwork for your iPhone, etc.
    3 August 2009 - Technically, it is tomorrow, but I'm still calling it the 3rd.

    On Friday, the water meter was installed, but when we tried opening the valve, water sprayed out somewhere inside of the bathroom wall. Later, when I examined the pictures of the wall internals I took before the drywall covered them, I could see that one of the PEX tubing clamps was missing - oops! Lynne's not entirely happy with the plumber as this means she will be painting part of the bathroom wall over again.

    On Saturday, Lynne painted sign letters while I touched up the curbs until my mind and hands were both numb and I couldn't do it any more. During this time, the overhead door installer began working on putting in the door but gave up when he could not find enough solid wood to mount the rails. Additionally, I cut an opening into the bathroom wall based on the picture and sure enough, there was a PEX clamp missing.

    On Sunday, Joel and I made two trips with my dad's pickup truck to select, load, and unload the materials for the framing of the buildout. It took two loads and about 4 hours, including a short break for lunch. The plumber came to fix the plumbing and we had a working bathroom by the end of the day.

    Early this morning, I went over to the building for about an hour to straighten out the problems with the overhead door installation. The installer was having troubles making it fit with only the 4" posts on either side of the opening. After I flipped the brackets so that the lag bolts hit solid wood, he was in good shape and had it installed later in the day.

    After dinner, Lynne, Joel, and I went over and I framed out the cellar with the occational help from both Lynne and Joel when we needed to stand up a wall. When Lynne wasn't helping me, she continued to paint the sign letters (you can see the red F) and Joel was also a big help doing the various tasks which he was assigned. Perhaps tomorrow night we will install the ceiling joists above the cellar.


    30 July 2009 - Last night I removed the forms from the concrete curbs and ground the offending edges. I also setup our giant stainless steel sink and mounted and began plumbing the two faucets. This morning, Lynne began working on painting the sign and a large old mirror for the bathroom. My next job is to touch up the coarse spots in the concrete.

    Chris at Graphic 22 let me know that our T-shirts and window vinyl are about to be completed, so we're looking forward to sporting some new Ts and covering over the ugly window.

    28 July 2009 - Just when I thought that I had solved the NIPSCO electricity problem, my building owner called me to say that NIPSCO had put the new meter's billing into his name. Calling NIPSCO to resolve the problem was only made slightly more difficult by my not yet having an account number for reference, but fortunately I had our federal ID number and the phone number under which I had registered the account. Strangely, the automated system was unable to use that same phone number to locate my account. Upon reaching a human, I was told that I had not provided my payment confirmation number, which I explained that I most certainly had, and that it seemed unlikely that NIPSCO would have set the meter without it. Getting past this little hurdle, I was asked what I would like the meter back dated to, which seemed obvious to me as there had been no meter until it was set. Finally, they asked me some information about what the company does. Remarkably, they weren't able to figure it out from our name - one has to wonder...
    27 July 2009 - Yesterday, while I was working on putting up some FRP in the area where it will be more difficult after the plumber finishes his work, Shaun showed up to see the facility and to help. Unfortunately, I was ready to head home, but I mentioned that I would probably be back in the morning around 7a for a couple of hours if he wanted to help at that time. Later Sunday, Lynne, Joel, and I went into Chicago to a friend's birthday party and we didn't arrive home until about 1:30a this morning. At about 7:30a this morning, I was still pretty tired (but not as tired as I am right now) and then it dawned on me that Shaun might have called to see if I was working in the morning, so I checked my phone. Sure enough, Shaun had left me a message, so I called him back and setup to meet him at F8 at 8:15a. We worked on putting up a couple more sheets of FRP, then he mentioned that he knew the dispatcher for the local concrete plant and so we calculated how much we needed (1.5 cu yd) and called - they could have a truck out at 11a - we placed the order. Next I called my dad who is an expert in all things and because we just plain needed the help. The truck arrived and the three of us worked like dogs for about 2.5 hours. I was seriously afraid that we weren't going to be able to do all of the troweling before it setup and that we were going to have a huge mess of unfinished concrete filling our precious forms. I couldn't have asked for any better help and we couldn't have done it with any fewer. Many thanks to both my dad and Shaun for stepping up to the plate when it mattered. Now that the concrete is in, we need to let it cure for about seven days and then we can start putting up walls and all...
    24 July 2009 - NIPSCO came yesterday and set the meter. Of course it wasn't quite that easy. The first visit by the young installer yielded a refusal to install because the label written on the meter panel to designate the meter as the one for our suite did not meet some prescribed standard. The installer said that a sticky label must be applied and that he would stop by again later in the day. I consulted with the building owner, went to the store and picked up a pack of vinyl labels, and stuck a letter D on the meter panel. I also noted that another meter had been previously set at our building with only a label written in marker as had all of the meters at another new local building holding the new post office (which I stopped at on the way to the store). Clearly this installer was just being a stickler. At any rate, we now have power to our suite, making working at night much easier.

    Lynne has been busy painting the bathroom and the plumber has been busy putting in the new French floor drains. Once the plumber is done making a mess, I will build the forms for the concrete curbs and we'll pour all of the concrete for the drains and curbs at the same time.

    22 July 2009 - The paint went on yesterday and looks good. Lynne painted the ceiling of the bathroom last night while I glued all-thread rods into the floor to secure the forms for cement curbs which will contain any water within my space. I am taking most of today off in order to setup shop and do some work at the building. I hauled in the lumber for the curb forms and did some electical wiring. Then I began the process of setting up new electrical service with NIPSCO, only to find that while they are one of the highest rate electricity/gas companies in the country, they certainly don't invest that income into technology. The process went something like this:
    Call NIPSCO to setup new service, only to find out that they have outdated building information, so they don't show Suite 105 as existing.
      - Call the building owner and we laugh together about how the NIPSCO engineer has failed to call him back about getting things like this resolved. He tells me to use the old numbering scheme.
      - Call NIPSCO to setup new service using outdated information. Am told I have to make a setup payment either via web site or phone and then call back with confirmation number. I choose web site so don't take down phone number. Also have to fax corporate information over, no email.
      - Go to local copy shop to fax info.
      - Go to web site to make payment. Cannot make payment because account is not yet setup.
      - Call NIPSCO to setup new service and get payment phone number. Learn that previous person I talked to should not have said I could pay via web site. No kidding... Also learn that if I pay by direct transfer (which they call check) it is only $1.75 and if I pay by debit or CC it is $25! I choose "check".
      - Call payment phone number and make payment to get confirmation number.
      - Call NIPSCO to setup new service and report confirmation number. Answer twenty questions to ensure I am supposed to be accessing business account. I tell them my confirmation number. Am told that they don't have my fax documents yet. I tell them I sent them over about 10 minutes ago. They say that it may take up to 24 hours for them to receive the documents and ask if I indicated a contact phone number on the documents. I say yes, even though I was not told to do so, I had fortunately included that information.
      - Waiting for NIPSCO to call me back. I hope it isn't the engineer that never calls back...
    20 July 2009 - This weekend saw some progress as the drywall is nearly finished in the main portion of the building, allowing the painter to do his job on Tuesday. This will complete the portion of the work which is preventing my buildout from beginning.

    In order to keep myself busy while I am impatiently waiting to get started on the construction, I began work on the sign for the outside of the building. It is made from a 4' by 4' square of 3/4" plywood with the logo cut from similar plywood and fastened to the front. The large F in the middle is 1-1/2" thick and is spaced out in order to allow a rope to be tied around it in a figure eight, as on the logo. The next step is to prime and paint the wood.

    When I look at this picture I cannot help but think that the sign needs to be bigger, but this is as tall as the space on the side of the building will allow and it is probably more that Joel has grown up so much, rather than that the sign is small...

    16 July 2009 - The drywall in the main portion of the building is nearly done, as can be seen in this photo of our space before we've added anything to it. The size is a bit difficult to judge until you know that the plywood square is where our 8'x8' overhead door will go and that Lynne, our "brewery girl" is standing in the corner.

    We are keeping the room clear of materials in order to allow our painter to spray a sealer coat to the main box. Then the floor drains will be cut in and plumbed, followed by concrete curbs to contain any water within the 12'x20' refrigerated "cellar" and production areas. My office and storage will be above the "cellar" and a 10'x21' retail space in the front of the room will be partitioned with 8' half walls. A corner of the retail space is being reserved for a small climbing wall, which will finally provide a use for the auto-belay that I purchased a couple of years ago.

    13 July 2009 - Our new logo is done! One of my other passions is pinball, and having worked in the industry for almost 7 years, I met a lot of very talented people. Greg Freres, a most excellent artist and co-worker from my days at Williams agreed to help me with my logo and labels. His talents have truly shown with this new design, and I am very much looking forward to his future works when we are ready to put together our first labels.

    Pinball titles for which Greg is credited (by year) include: Harlem Globetrotters On Tour, Rolling Stones, Hotdoggin', Skateball, Frontier, Fathom, Vector, Speakeasy, Speakeasy 4, BMX, Mysterian, Black Pyramid, Hot Shotz, Lady Luck, Karate Fight, Black Belt, Strange Science, Hardbody, Escape from the Lost World, Elvira and the Party Monsters, Dr. Dude, Party Zone, Star Trek: The Next Generation, No Fear: Dangerous Sports, Scared Stiff, Medieval Madness, and Revenge From Mars.

    10 July 2009 - We will occupy one of five spaces in a newly constructed building on the west edge of town. Our space is just about ready for us to start our portion of the buildout as the electrical and basic plumbing are in and the insulation and drywall for the exterior of the main room are due to be completed by next week. The floor cuts for the french drains will also be done in the next few days, allowing us to begin setting the forms for the concrete curbs which will contain any water during wash downs. The space is only 1400 sqft with a 16 ft ceiling, but the layout will allow us to have a small retail space out front with a few seats, a pinball machine, and eventually a small climbing area in the corner. A mezzanine level above the cellar will provide a small office space as well as storage.

    The refrigeration unit for the cellar has been sitting in my garage for a few weeks now and the glycol chiller components are in storage until the space is ready for them. Our brite tanks have been waiting to ship for about three weeks, our stock of new 1/2 BBL kegs is also waiting to ship. Our custom brew kettle and fermenters were just completed and will be ready to ship soon, so once we finish the construction, there will be a great deal of action. I can hardly wait!

    7 July 2009 - Our neighbor, Brickworks of Hobart, is in the local newspaper: The Times.
    5 July 2009 - The sad news of the death of climbing legend John Bachar.
    1 July 2009 - Follwing the city site review meeting on June 30th, our story was first made public on the front page of our local newspaper: The Times.

    Last updated: 4 January 2011 Copyright 2009-2011 Figure Eight Brewing LLC,
    All rights reservered.